VA Medical Center Long Beach

Healthcare / Seismic Retrofit

Base isolation installed without interrupting patient care

NYA’s Role:
Seismic Strengthening and Base Isolation
Location:
Long Beach, California
Owner:
Department of Veterans Affairs
Project Partners:
AC Martin Partners (Architect)
Construction Cost:
$60 million
Area:
300,000 ft²
Status:
Completed 1995

Overview

The VA Medical Center in Long Beach, California, was an essential facility. It had to remain fully operational during and after a major earthquake. A seismic evaluation concluded that the 300,000-square-foot building had insufficient strength and ductility to do so.

NYA provided seismic strengthening and base isolation for the hospital, with AC Martin Partners as architect. The retrofit was completed in 1995.

Challenges

The retrofit had to meet the standard of an essential facility in a building that could not close:

Insufficient Seismic Capacity
The evaluation found that the building lacked the strength and ductility to stay operational through a major earthquake.
Essential Facility
As an essential facility, the hospital had to remain fully operational during and after a major earthquake.
An Operating Hospital
Patients and services had to continue as normal for the whole of construction.

The retrofit had to add that capacity without disturbing the work of the hospital.

The VA Medical Center hospital tower in Long Beach, its white louvered facade rising behind street trees

The hospital stayed in service throughout the retrofit

Solutions

NYA identified seismic isolation as the most suitable strategy for the retrofit. Isolation bearings decouple the building from horizontal ground motion, reducing the forces the structure above them has to resist.

To keep the hospital running, construction operations were confined to the outside of the building. NYA positioned the seismic isolation bearings in the crawl space beneath the basement and first-floor slab, so the floors above stayed in use.

A concrete column flaring into the floor above, seated on an isolation bearing wrapped in a protective cover in the crawl space beneath the hospital

Outcomes

The Long Beach VA Medical Center was the first hospital in the United States to be retrofitted without interrupting patients or services.

Since the original base isolation, NYA has continued to work across the campus, from structural evaluations and planning to new construction, renovations and demolition.

Continuing Work on the Campus

  • Campus master plan
  • Critical building survey
  • Structural evaluation of multiple campus structures
  • Building 2 seismic study and deficiency review
  • Water tower upgrade
  • Site water distribution system
  • Police and engineering building
  • Canopy and parapet for the new police building
  • Demolition of Buildings 3, 3 Annex, 5, 13 and 47
  • Building 200 chapel renovation
  • Building 126 nuclear medicine relocation and new conduit installation
  • Camera mounts for the new gait lab
  • Livewall
  • Basement sewer trench
The campus water towers: a concrete tank on a single column beside a steel tank on braced legs

Capabilities and Structural Systems

  • Seismic Evaluation
  • Seismic Isolation Retrofit
  • Seismic Strengthening
  • Essential Healthcare Facilities
  • Construction in an Occupied Hospital
  • Campus Structural Surveys
Workers setting an isolation bearing beneath a column in the crawl space in April 1995, with jacks carrying the column load